Nammuldi, Western Australia
Due to the length of this switchroom the transportation of the finished product needed to be considered.
Our team of engineers designed the 37 m structure into two sections, fully constructing the switchroom office offsite. It was then dismantled and transferred in two sections via truck to be successfully re-joined and commissioned on the mine site.
Frame: Structural Steel SHS supportsWall: 0.42 mm Colorbond sheeting with XFlam internal panellingRoofing: Colorbond Monoclad sheetingInsulation: Fibreglass with aluminium foilLandings and Stairs: Galvanised open grateVESDA Fire suppression system
Length37 mSpan5.3 mHeight3
Overcoming the transportation issue was a successful achievement for our engineering team.